Infrasource, the PECO subcontractor, is currently working on the 200 block of West Gay Street. This work is being done from 7 a.m. to 4 p.m. Monday thru Friday. If Infrasource follows the current pace of work, they will be on this block for the next six weeks.
Infrasource is still waiting to set a manhole at the corner of Gay and Church street in front of Malena’s Vintage Boutique. One of the hold ups has been a wire that runs through the area the new manhole has to be placed. Infrasource and the borough have not determined if that wire is still live.
As a reminder, once work on Gay Street is complete, Infrasource will begin working on the cross streets. The affected blocks will be the 100 block of N Darlington St, the 100 block of N Church St, and the 50 and 100 blocks of N High Street.
We will be sure to keep you updated on which block is affected as the work progresses.